The Wire

Energy news from Omaha Public Power District

General

Video: OPPD tackles a massive move

April 12, 2022 | Wire Staff | reliability, T&D
T&D_Transformer Move 2022 intersection
Workers recently moved a new autotransformer from OPPD’s Elkhorn Service Center to its new home at substation in northwest Omaha. Photo by Danielle Beebe-Iske

In the middle of a cold night, while most were sleeping, OPPD workers and contractors were hard at work on a major move.

Over an eight-hour stretch, they worked carefully to move an autotransformer weighing more than a half million pounds from the Elkhorn Service Center to a substation in northwest Omaha.

T&D_Transformer Move 2022 tires
The specialized rigging system used to move an autotransformer was 400 feet long and had more than 200 tires. Photo by Danielle Beebe-Iske

The move required a heavy-haul trailer with 40 axles to distribute the weight. The combined weight of the autotransformer and the trailer used to move it totaled more than 1 million pounds. Several semi-trucks provided support.

The move also required months of planning. OPPD collaborated with the City of Omaha, the Nebraska Department of Transportation and law enforcement to gain permission and permits.

“Replacing a large piece of equipment like this requires extreme coordination – from ensuring we are not interrupting service to our customer-owners during the transition, to making sure we can safely deliver it to the place it needs to be,” said Nick Hardesty, the project manager for the move.

How to move an autotransformer

“This autotransformer took nearly two years to build, 11 days to transport to Omaha by rail and over eight hours to safely move from the railyard to its final destination,” he said.

T&D_Transformer Move 2022 lights
During the move, crews raised traffic signal support arms to make room for the over-sized load. Photo by Danielle Beebe-Iske

The move began at 8 p.m. on a recent Sunday. A safety briefing was held to ensure everyone was aligned on the process and aware of any safety hazards.The trailer traveled at less than 10 miles per hour to reach its final destination around 4:30 a.m. the next morning.

Law enforcement blocked off roads and crews raised traffic signal support arms to make room for the over-sized load.

“The autotransformer movement from Elkhorn Center to the substation went very smoothly,” Hardesty said.

“I’m just blown away by everything the project team and support personnel have done,” he said. “I’m just thankful to be a part of this OPPD team and help where I can.”

Delivering reliable power

More work remains to energize the autotransformer, Hardesty said.

T&D_Transformer Move 2022 unit closeup
The gray structure here is the autotransformer that was moved to a northwest Omaha substation recently. Photo by Danielle Beebe-Iske

Teams will install accessories and run wiring to connect the autotransformer to the electrical grid. Once connected, the manufacturer will test it to ensure it is fully functional.

The autotransformer replaces one that had been part of the system since 1972. Workers broke it down for scrap metal. It was the oldest in OPPD’s system and was nearing its end of life.

“This project was an investment in our grid to ensure we continue to provide our customer-owners reliable power every time they want to turn on a light or charge a laptop,” said George Seliga, principal engineer for the project. “The size and scale of this autotransformer puts a spotlight on the complex infrastructure we have in place to support that reliability.”